Key Features and Benefits
Yau Pok Road, Yuen Long
- 2 156 units completed with about 880m2 of ancillary facilities, resident intake commenced by phases from 28 March 2025. It was the first completed Light Public Housing project which took only 379 days from design inception to project completion.
- Spanning an 87,000m2 site divided into northern and southern zones, the project features 10 three-storey residential blocks and 8 single-storey ancillary buildings, as well as 2 public transport termini. Designed with a courtyard layout, half of the flats overlook central green courtyards with lush landscaping and seating areas, while the rest benefit from serene farmland views. By adopting the MiC method, the project minimised on-site construction activities to significantly reduce noise and air impact, safeguarding the local wetland ecosystems, migratory birds, and neighbouring communities.