Implementation of Light Public Housing - the Second Batch of Projects

Project Code001HL
Project TitleImplementation of Light Public Housing - the Second Batch of Projects
LocationEastern / Kwun Tong / Northern / Shatin / Tuen Mun / Wong Tai Sin
Contact PersonCPM202
Project TypeHousing
Building TypeLight Public Housing
Estimated Project Cost>=$500M
Project Start2023-24
Scheduled Project Completion2026-27
Current ContractsContract No. : SSM520 (NEC4 ECC Option C) (for site at Siu Lam)
Contract Sum : $2,020M
Contractor's Name : Able - Chun Wo Joint Venture

Contract No. : SSM521 (NEC4 ECC Option C) (for sites at Chai Wan and Tuen Mun)
Contract Sum : $3,198M
Contractor's Name : Able - Chun Wo Joint Venture

Contract No. : SSN516 (NEC4 ECC Option C) (for sites at Ma On Shan and 5 nos. of vacant school premises)
Contract Sum: $808M
Contractor's Name : Yau Lee Construction Company Limited

Contract No. : SSN520 (NEC4 Supply Contract) (for Construction and Delivery of Habitable MiC Modules for sites at Chai Wan, Ma On Shan, Siu Lam and Tuen Mun)
Contract Sum: $2,033M
Contractor's Name : CCSIC GreenTech - Aluhouse Joint Venture