Construction of Fire station-cum-ambulance depot with departmental quarters and facilities of the Fire Services Department at Anderson Road Quarry Site, Sai Kung
| Project Code | 177BF |
|---|---|
| Project Title | Construction of Fire station-cum-ambulance depot with departmental quarters and facilities of the Fire Services Department at Anderson Road Quarry Site, Sai Kung |
| Location | Kwun Tong |
| Contact Person | CPM203 |
| Project Type | Public Safety |
| Building Type | Fire Services |
| Estimated Project Cost | >=$500M |
| Project Start | 2025-26 |
| Scheduled Project Completion | 2029-30 |
| Current Contracts | Contract No. : SSP504 (NEC ECC HK Edition Option C) Contract Sum : $1,032M Contractor's Name : Shui On Joint Venture |